In May 2005, the government of Pakistan started implementing a series of integrated activities in line with the power sector development strategy it adopted under its Medium-Term Development Framework, 2005–2010. The strategy envisaged additional power generation, transmission, and distribution capacities to ensure sufficient electricity supply to meet the projected 8% per annum growth over the plan period. Subsequently, the power distribution companies (DISCOs), in coordination with the Ministry of Water and Power, prepared the Power Distribution Sector Road Map 2008–2017. The road map recommended short- (priority), medium-, and long-term system improvement projects and detailed the investment needs.
The total investment requirement for the DISCOs from 2008 to 2017 was estimated at $5.2 billion. The government sought financing from the Asian Development Bank (ADB), the World Bank, and other multilateral and bilateral funding agencies to meet this requirement. In response, ADB approved the Power Distribution Enhancement Investment Program, a multitranche financing facility (MFF) for $810 million. Tranche 1 of the MFF was approved in September 2008, comprising two loans worth $252 million. Tranche 1 project’s envisaged impact was improvement in the distribution infrastructure and management. Its intended outcome was removal of power system bottlenecks, resulting in the reduction of transmission and distribution losses through distribution system rehabilitation, augmentation, and expansion covering the eight DISCOs.
The project included physical investments in subprojects covering (i) secondary transmission grid (STG) augmentation, extension, conversion, and rehabilitation; (ii) STG transmission lines; and (iii) energy loss reduction through the installation of capacitors. Its aggregate expected output was the completion of 146 subprojects adding 2,200 megavolt-amperes (MVA) of transformer capacity, reduction in losses, increase in reliability, and improvement in power quality. Because of savings, 180 subprojects were completed by project closing. Through these subprojects, 2,588 MVA of transformer capacity and 24 kilometers (km) of transmission lines were added to the system. The outputs have supported operational load and system management, ensured more reliability and quality of power supply, improved voltage profiles, and reduced energy losses. More importantly, the outputs have enabled the DISCOs to serve more customers and provide relief to the existing overloaded network, improving electricity sales and revenues.
For medium- and low-voltage networks, 23 subprojects to reduce energy loss and improve distribution were successfully executed. Besides distribution capacitors, they comprised distribution transformers, construction equipment, switchgear, energy meters, and maintenance equipment, altogether causing energy losses to drop to 18.76% at project completion against the target of 20.60%.
At the impact level, the project helped to increase electricity sales by 11,000 gigawatt-hours (GWh) in 2015. This was 1,000 GWh short of the target, but nonetheless indicates good improvement in the electric distribution capability of the DISCOs. Village electrification rates improved substantially, increasing from 61.2% in 2007 to 79.7% in 2015, well above the 75% target. Overall outages in the Pakistan Electric Power Company (PEPCO) system were reduced by 9% in 2015 compared with 2009.
The Pakistan Electric Power Company (PEPCO) served as the executing agency, and the DISCOs, the implementing agencies.