Lessons

Horizontal Tabs

Lessons
Background

Assam, known for its large tea and petroleum industries, has the largest economy in the northeastern region of India.  But it has lagged behind the rest of India in terms of growth and investment climate.  Its economic activities have been significantly constrained by inadequate power supply and limited access to electricity.  One of the bottlenecks in Assam’s power sector was the limited capacity of its transmission and distribution (T&D) systems, which made it difficult to provide reliable power to consumers.

To help address the situation, the Asian Development Bank (ADB) approved a $200 million multitranche financing facility (MFF) for the Assam Power Sector Enhancement Investment Program in November 2009.  The MFF was designed to support the government’s T&D investment program, which aimed to (i) strengthen power transmission capacity to deliver reliable and affordable electricity, (ii) improve access to electricity, (iii) enhance efficiency and quality of power supply, (iv) fully operationalize unbundled utilities of the Assam State Electricity Board (ASEB), and (v) promote private sector participation through innovative distribution franchising models. It planned to establish a solid foundation for a sustainable state power sector with increased transmission and distribution capacity to support inclusive economic growth.

At the impact level, this project, the second of four MFF tranches, sought to contribute to a sustainable state power transmission subsector to support inclusive and low carbon economic growth. Its expected outcome was enhanced quality and expanded service delivery of electricity in Assam through improved technical, commercial, and financial performance and capability of power utilities.  Its impact and outcome were to be achieved through two outputs: (i) access to power (transmission) that involved constructing new transmission lines and substations and other transmission system improvements; and (ii) energy efficiency enhancement (transmission loss reduction) through extended, augmented, and refurbished transmission substations and reactive compensation.

At completion, the project largely achieved its output targets.  Under output 1, 8 new substations were constructed, transmission lines were extended, and ground wire was upgraded to optical pilot ground wire (OPGW).  Due to inadequate land, a change was made in the design of a substation, but this did not affect the project scope and outcome. A reduction in the length of transmission lines resulted from the optimized route alignment after detailed design. To use tranche 1 loan savings, upgrading to OPGW was completed under the previous tranche.

Under output 2, 19 existing substations were augmented, and 12 others were refurbished. This increased the capacity of existing transmission substations as planned, and consequently improved the energy efficiency and reliability of supply in selected high load centers.

Because of successful output deliveries, the project fully achieved its intended outcome, in some cases, exceeding targets albeit with delay.  It helped increase the state transmission system capacity from 766 megawatts in 2008 to 1,960 megawatts in 2018, alleviate the transmission loading level from 95% in 2008 to the 75%–80% range in 2018, and reduce transmission loss from 6% to 3.55% during the same period. Given the expected synergistic effect of investments in the sector, the increase in the total transmitted electricity and transmission loss reduction in Assam are the collective results of all the related investments, including tranche 1 and other government projects that were simultaneously implemented with this project.

Corrective actions were facilitated by ADB to address initial difficulties in implementing safeguards measures that resulted in local protests over land compensation.  All compensation, complaints, and requests were settled prior to project completion.

At appraisal, the government of Assam and the Assam Electricity Board (ASEB) were designated as executing agencies (EAs).  But under the state power sector reform process, the government of Assam formally dissolved and reorganized the ASEB, and in March 2013, transferred ASEB’s functions to three entities: the Assam Power Distribution Corporation Limited, the Assam Electricity Grid Corporation Limited (AEGCL), and the Assam Power Generation Corporation Limited. Since then, the AEGCL had served as the EA. The project management unit under the erstwhile ASEB continued to function as the coordinating agency.

Project Information
Project Name: 
Assam Power Sector Enhancement Investment Program (Tranche 2)
Report Date: 
October, 2020
Main Sector: 
Country: 
Project Number: 
Report Type: 
Project/Modality: 
MFF
SDG: 
Goal 8: Decent Work and Economic Growth
Goal 9: Industry, Innovation, and Infrastructure
Loan Number: 
2677
Source of Funding: 
OCR
Date Approved: 
5 October 2010
Report Rating: 
Successful

Browse Lessons By:

Evaluation-Lessons.org uses cookies to improve your user experience. To learn more, click here to view our cookie policy. By clicking on OK or continuing to use the site, you agree that we can place these cookies.