Lessons

Horizontal Tabs

Lessons
Background

Fact-finding mission by the Asian Development Bank (ADB) in the aftermath of the March−June 2014 severe flooding in northern Afghanistan revealed extensive losses to rural infrastructure, but it was not possible to visit some areas and undertake a comprehensive assessment because of security issues.  To support the government's efforts to rehabilitate the damaged irrigation and road infrastructure, ADB made use of the results of the damage and needs assessments (DNA) undertaken by two agencies, the Ministry of Rural Rehabilitation and Development (MRRD) and the Ministry of Energy and Water (MEW), in preparing the Northern Flood-Damaged Infrastructure Emergency Rehabilitation Project. 

The project was to help rehabilitate (i) small-scale irrigation and rural road infrastructure in 15 of the worst-affected provinces selected on the basis of MRRD’s DNA and (ii) larger-scale irrigation system infrastructure in 3 provinces identified based on MEW’s DNA.  It was approved by ADB for a grant of $40 million from the Asian Development Fund and another grant of $16.66 million from the Afghanistan Infrastructure Trust Fund in October 2014. At approval, the project’s envisaged impact was improved community welfare in flood-affected project areas, with a target that by 2020 the average poverty rates across the project provinces would be reduced by 5% from the 2014 baseline of 44.5%. Its expected outcome was irrigated agriculture and access to markets restored, with a total of 48,280 hectares (ha) of agricultural land under traditional irrigation schemes and 16,500 ha under formal schemes brought back to production by 2018. The outcome was to be achieved through two outputs: (i) selected flood-damaged infrastructure rehabilitated and (ii) project management supported.

During implementation, a number of subprojects were substituted, and the project’s geographic scope was expanded twice at the government’s request, with 6 provinces added in July 2015 and 6 more in March 2016.  The additional provinces were not originally included because of time constraints in conducting a proper assessment of the areas. Along with the expanded scope, additional contract packages were approved, and output targets were adjusted.  The MRRD undertook 853 contracts with community development councils (CDCs), 745 of which were for the rehabilitation of traditional schemes and 108 were for rural roads. All the subprojects were successfully implemented, in most cases, exceeding targets. Key criteria for subproject selection were that (i) assets were damaged by the 2014 floods and (ii) repairs were technically feasible, cost-effective, financially sustainable, and economically viable.  The CDC subprojects created at least 81,000 short-term and permanent jobs. The MEW completed the works on 8 formal schemes involving the rehabilitation and reconstruction of weirs, intakes, spillways, canals, protection walls, retention walls, and wash protection structures.

Successful delivery of targeted outputs enabled the project to overachieve its planned outcome.  A total of 82,939 ha of flood-affected land were brought back to production.  Infrastructure and flood control works covered a preexisting irrigation area of 154,154 ha, and an additional irrigation area of 7,324 ha.  A project impact assessment survey conducted in December 2017 revealed that the project had a major impact on farm households, increasing income levels and food security for smallholder farmers.  It estimated that 4.09 million adults benefited from the project; 130 villages had improved road connectivity; road, bridge and culvert construction saved 37% in travel time; and transport rental costs declined by 31%.  The CDC community mobilization and capacity developed by the project will benefit the conduct of other livelihood and social activities in the communities. The institutional implementation capacity built in the local government offices of the MRRD and the MEW will benefit future projects.

The project had the Ministry of Finance as executing agency.  The MRRD and the MEW, as implementing agencies, mobilized their project management offices to team up with their provincial-level project implementation units or project implementation office in carrying out the project activities.

Project Information
Project Name: 
Northern Flood-Damaged Infrastructure Emergency Rehabilitation Project
Report Date: 
September, 2020
Country: 
Project Number: 
Report Type: 
Project/Modality: 
Project grant
emergency assistance project
SDG: 
Goal 2: Zero Hunger
Goal 9: Industry, Innovation, and Infrastructure
Goal 12: Responsible Production and Consumption
Loan Number: 
G0411, G0412
Source of Funding: 
COL/ADF, Afghanistan Infrastructure Trust Fund
Date Approved: 
16 October 2014
Report Rating: 
Successful

Browse Lessons By:

Evaluation-Lessons.org uses cookies to improve your user experience. To learn more, click here to view our cookie policy. By clicking on OK or continuing to use the site, you agree that we can place these cookies.