Lessons

Horizontal Tabs

Lessons
Background

Under its Welfare Improvement Strategy, 2008–2010, the government of Uzbekistan identified

improving water supply and sanitation (WSS) services as a national priority.  The Asian Development Bank (ADB) aligned the Water Supply and Sanitation Services Investment Program with the national WSS policy framework, which called for greater institutional effectiveness, better service performance and management, improved operational and commercial efficiencies, higher cost recovery rates, and tighter financial controls. In August 2009, it approved a multitranche financing facility (MFF) not exceeding $300 million to finance the program, and in October 2009 approved tranche 1 of the MFF for a loan of $60 million to Uzbekistan.

The tranche 1 project aimed to improve the living standards, environment, and public health of urban centers in Bukhara, Navoi, and Surkhandarya provinces. Its expected outcomes were (i) safe, reliable, and sustainable water supply for 360,000 residents in 11 district centers in Bukhara and Navoi; and (ii) improved sanitation services and hygiene for people living in Termez.  Besides physical rehabilitation and construction works, the project also intended to provide the executing and implementing agencies with necessary support in project management and institutional strengthening of WSS operators.

At completion, the project achieved all its planned physical outputs, in some cases surpassing targets.  Against a target of 13.2 kilometers (km), the water trunk mains delivered reached 25.6 km.  Water distribution networks reached 318.1 km, compared to a target of 286 km. With large physical improvements, the number of beneficiaries reached nearly 797,000.  The water treatment and distribution capacity of the project suvokavas (water operators) also substantially rose, and system leakage in all the suvokavas dropped to less than 30%. Water quality has improved significantly and is compliant with national drinking water standards.  

However, despite significant improvements in infrastructure and the number of beneficiaries, as of project completion review, water was being supplied only for six hours in some Bukhara and Navoi project areas.   Household connections were insufficient and some suvokavas have been prompted to supply water intermittently to prevent the excessive use of water for irrigation. By rehabilitating the existing wastewater treatment plant (WWTP), the project helped improve wastewater treatment and sewage collection in Termez, albeit 9% short of the targeted 70% operational capacity.

The project also encountered significant shortfalls in achieving its nonphysical targets. Designed policy and institutional reform measures, such as the implementation of performance-based service contracts and lease contracts, the district water utility rationalization study, performance benchmarking, tariff study, and capacity development of responsible government agencies—were only partially achieved. Reasons for their partial attainment were largely technical and systemic, and included (i) significant delays in consultant recruitment; (ii) insufficient capacity in the executing agency (EA); (iii) changes in the WSS institutional and legal framework; (iv) availability of grant funding for WSS institutional reforms, resulting in EA reluctance to use loan funds for the same purpose; and (v) the government’s evolving priorities, particularly toward reform efforts in billing, collection, and fiscal discipline and controls. Most nonphysical activities were also complex and could not be implemented within the given circumstances.

Because of inadequacies in WSS provision and shortcomings in policy and institutional reforms and capacity building, the project only partially achieved its outcome targets. Nevertheless, as it improved the supply of safe and reliable drinking water to the project areas and those connected to the Damkhoja interregional trunk main, the development impact of the project has been significant.  The government reported a major decline in the incidence of infectious diseases in the project provinces from 2011 to 2016, partly because of the project. Cost and time savings due to better access to water supply have been most important for the poor. Improvements in the health and quality of life of the poor have been remarkable particularly in the rural settlements served by the Khatirchi district suvokava where people used to consume untreated canal water for lack of other sources.

The project had the Agency “Kommunhizmat” as executing agency (EA).  A program preparation and management unit (PPMU) and three project implementation units (PIU), one each in the three project provinces, initially took charge of day-to-day project activities.  Following government decision to streamline the implementation of projects funded by international financial institutions, and with prior ADB approval, the EA restructured and combined the PPMU and the PIUs into a new project coordination unit in 2015.

Project Information
Project Name: 
Water Supply and Sanitation Services Investment Program (Tranche 1)
Report Date: 
January, 2020
Country: 
Project Number: 
Report Type: 
Project/Modality: 
MFF
SDG: 
Goal 3: Good Health and Well-Being
Goal 6: Clean Water and Sanitation
Goal 11: Sustainable Cities and Communities
Loan Number: 
2564
Source of Funding: 
COL/ADF
Date Approved: 
8 October 2009
Report Rating: 
Successful

Browse Lessons By:

Evaluation-Lessons.org uses cookies to improve your user experience. To learn more, click here to view our cookie policy. By clicking on OK or continuing to use the site, you agree that we can place these cookies.