Lessons

Horizontal Tabs

Lessons
Background

The transport sector was the largest recipient of the Bangladesh government’s investments over the past two decades. It accounted for about 20% of the total annual expenditures from 1999 to 2017. Three-fourths of the sector investment went to road transport, which expanded significantly at the expense of rail transport.  As a result, the market share of railways decreased steadily from 30% in 1973 to 4% in 2005. A vicious cycle set in ─ limited investments led to declining quality and efficiency, which in turn led to poor traffic and high operating ratios. Exacerbated by the Bangladesh Railway's poor financial performance and ever-increasing dependence on government budget support, the ability of rail transport, which is environment-friendly and requires less land per unit of operation, to contribute to the country’s development was greatly eroded.

To help address the situation, the Asian Development Bank (ADB) approved a $430 million multitranche financing facility (MFF) for the Railway Sector Investment Program in October 2006. The program was to improve rail sector performance by (i) supporting policy, organizational, and legal reforms to restructure Bangladesh Railway into a market-oriented business organization with improved financial governance, human resource, and operational systems; and (ii) financing economically and financially viable investments in key rail corridors.  Collaborative cofinancing was provided by the Japan International Cooperation Agency for $116.7 million and the Export–Import Bank of Korea for $22 million.

The program envisaged contributing to sustainable economic growth and poverty reduction, as impact; and improving rail sector performance through enhanced efficiency, as outcome. It was expected to implement a comprehensive set of interventions for the Bangladesh Railway to become a commercially focused service provider with improved governance and safety.  Far-reaching sector reforms were to be combined with investments to decongest critical sections, enhance safety and increase traffic on existing lines, and replace ageing coaches to provide more comfort to passengers.  The reform and investment components were integrated: approval of the investment subprojects depended on the implementation of specific reform actions.

Under the investment component, 8 subprojects were planned at appraisal; however, at completion, the program delivered only 4 subprojects, one of them partially.  Key outputs included (i) signaling modernization and meter gauge double tracking of Tongi–Bhairab Bazar railway, (ii) yard improvements and extension of loops in 8 stations between Dhaka and Darsana and at Sirajganj Bazar, (iii) signaling upgrade in 11 stations between Dhaka and Darsana, and (iv) procurement of 50 broad gauge passenger carriages and 100 meter gauge passenger carriages. Output 1 was covered by three tranches ─ tranches 1, 2, and 4 ─ instead of just tranche 1, as originally planned. Outputs 2 and 3 were covered by tranches 2 and 4, with unfinished works under output 3 taken up by another ongoing railway project. Output 4 was successfully delivered under tranche 3.  The output were delivered substantially in accordance with the periodic financing requests made for each MFF tranche.

Though progress was slow, Bangladesh Railway ultimately met most of the reform conditions covenanted in the MFF framework agreement and individual agreements for the five loans released in four tranches ─ tranche 1 with two loans, totaling $130 million, approved in February 2007; tranche 2 for $150 million, approved in December 2011; tranche 3 for $100 million, approved in December 2013; and tranche 4 for $50 million, approved in March 2016. Railway safety improved with the adoption of improved operational and maintenance standards, use of updated manuals for train operations, maintenance of track and permanent way, and signaling. Reform accomplishments under the program actions laid the groundwork for the ongoing rail sector reform in the country.

Substantial delivery of their intended outputs enabled each of the individual tranches to achieve their expected outcomes. However, due to the disconnect and inconsistencies between the targeted outcomes of the MFF and those of the tranche projects, the effectiveness of the individual tranches in achieving their planned outcomes did not end up with a similar result for the MFF.  On hindsight, the project completion review deemed the MFF as not the best modality because separate investment projects could have been financed more effectively along with a parallel policy-based loan for reform.

Nevertheless, because of the program’s physical investments, the number of trains increased by 22% between 2011 and 2017 and the passengers by 37% annually between 2011 and 2018.  Overall passenger traffic increased by 83.9% between 2005 and 2017.  The most critical section of the Dhaka–Chattogram corridor was decongested, lowering travel time and increasing train frequency and the revenues of the Bangladesh Railway.  Freight traffic started picking up with the deployment of new rolling stock in 2016−2017.   

Leaving behind critical lessons from the first use of the MFF modality in Bangladesh, the program had the Bangladesh Railway as executing agency.  The Bangladesh Railway established two units to take charge of day-to-day implementation ─ the reform implementation unit and the project implementation unit.

Project Information
Project Name: 
Railway Sector Investment Program - MFF and Tranche 3
Report Date: 
November, 2019
Main Sector: 
Country: 
Project Number: 
Report Type: 
Project/Modality: 
MFF
SDG: 
Goal 9: Industry, Innovation, and Infrastructure
Goal 8: Decent Work and Economic Growth
Loan Number: 
MFF: 0004, L3097
Source of Funding: 
OCR, JICA, COL/ADF, Export-Import Bank of Korea
Date Approved: 
MFF: 10 October 2006, L3097: 9 December 2013
Report Rating: 
MFF: Less than successful, Tranche 3: Successful

Browse Lessons By:

Evaluation-Lessons.org uses cookies to improve your user experience. To learn more, click here to view our cookie policy. By clicking on OK or continuing to use the site, you agree that we can place these cookies.