Lessons

Horizontal Tabs

Lessons
Background

Yap state, with a population of 11,400 during project preparation, is one of the four states of the Federated States of Micronesia. In 2013, it was 100% dependent on imported diesel for power generation on the main island. Due to high diesel costs, power tariffs were high, and the Yap economy was vulnerable to fuel price shocks. To reduce reliance on diesel, the Yap state decided to add renewable energy sources to its energy generation mix.  

Against this backdrop, the Yap power and water utility, the Yap State Public Service Corporation (YSPSC), designed the Yap Renewable Energy Development Project. The project's envisaged impact was improved energy security of the Yap state. Its expected outcome was YSPSC would supply an increased amount of clean, renewable energy. It had two planned outputs (i) installation of wind power generators, and (ii) installation of solar energy sources.

The Asian Development Bank (ADB) provided technical assistance (TA) for project preparation.  Based on a least-cost analysis, the TA consultants recommended that the project add 300 kilowatts (kW) of roof-mounted solar photovoltaics (PV); 1.4 megawatts of (MW) of wind turbines, comprising five 275 kW turbines to be installed in two phases; and a 1.8 MW medium-speed diesel. The recommendations were incorporated into the initial design of the project, approved by ADB for two loans aggregating $9.04 million in June 2013.  Some of the recommendations were revised, following the audit of the initial design by the design and supervision consultant (DSC).  The revisions indicated that the project would support Yap to achieve a 17% renewable energy penetration rate, against the original 22% projection.

At completion, the project constructed 3 wind turbines in a single phase, with a 90% confidence level output of 1.2 gigawatt-hour (GWh) per year. Commissioned in 2018, the smaller number of turbines was recommended by the DSC, which reassessed site conditions, considered permitting issues in further detail, and factored in newly available wind data.  Because of fewer turbines, the project produced only 1.5 GWh of electricity per year against the target of 2.6 GWh.  

Solar energy installed was, as proposed by both the TA and DSC, 300 kW. The installation was completed in 2016; however, with an actual capacity factor of 13% against the projected 17%, solar power produced during the monitoring period was only 0.35 GWh, against the target of 0.44 GWh. To better match varying load and allow for increased renewable energy penetration, two high-speed diesel generators, instead of a single 1.8 MW medium-speed generator, were put in place in 2017.  Against the projected outputs of 9.9 GWh per annum and 15 kilowatt-hour (kWh) per gallon efficiency, actual efficiency of the high-speed generators during the performance period was 13.1 kWh per gallon and actual output was 8.9 GWh.

Despite shortfalls in meeting its outcome targets, the project overall achieved its intended impact of improving Yap’s energy security.  It was able to reduce diesel imports by 25% by December 2019 from a baseline of 980,000 gallons in January 2012. Over the same period, actual diesel usage was 681,153 gallons, representing a 30% decrease. Its wind and solar installations contributed 17% of the 19.3% share of renewable energy in total generation, thus successfully achieving its revised penetration target. Actual reduction in carbon dioxide emissions from the 2012 baseline was 2,975 tons against a target of 3,000. However, allowing for a 5% increase in electricity demand between the base year and 2013, the actual carbon dioxide savings in 2013 amounted to 3,470 tons.  The project was responsible for 88% of this reduction.

YSPSC was the executing agency.  The DSC it engaged evaluated the initial project design, supported procurement, and supervised the contractors during implementation.

Project Information
Project Name: 
Yap Renewable Energy Development Project
Report Date: 
November, 2019
Main Sector: 
Country: 
Project Number: 
Report Type: 
Project/Modality: 
Project loan
SDG: 
Goal 9: Industry, Innovation, and Infrastructure
Goal 8: Decent Work and Economic Growth
Goal 13: Climate Action
Loan Number: 
3004, 3005
Source of Funding: 
OCR, COL/ADF
Date Approved: 
20 June 2013
Report Rating: 
Successful

Browse Lessons By:

Evaluation-Lessons.org uses cookies to improve your user experience. To learn more, click here to view our cookie policy. By clicking on OK or continuing to use the site, you agree that we can place these cookies.