In May 2005, the government of Pakistan began implementing a series of integrated activities to ensure adequate power supply to meet the projected 8% annual economic growth set out in its Medium-Term Development Framework, 2005−2010. Subsequently, in coordination with the Ministry of Water and Power, the power distribution companies (DISCOs) prepared the Power Distribution Sector Road Map, which recommended short- (priority), medium-, and long-term system improvement projects and detailed the investment needs. The total investment requirement for the DISCOs from 2008 to 2017 was estimated at $5.2 billion. The investments were to consist of improvements in the secondary transmission grid, power distribution, and energy loss reduction, to realize which the government sought financing from the Asian Development Bank (ADB), World Bank, and other multilateral and bilateral funding agencies.
In response, ADB approved an $810 million multitranche financing facility (MFF) for the Power Distribution Enhancement Investment Program in September 2008. To be provided in four tranches, the MFF focused on addressing distribution capacity shortfalls that at the time resulted in regular system outages and supply interruptions. The third tranche, covered by this report, supported physical investments to upgrade the secondary transmission systems through (i) i) new or upgraded substations, (ii) new transmission lines, and (iii) additions or augmentations to transformers within existing substations. It was approved for a loan of $245 million in December 2012 and was envisaged to finance 106 subprojects that were to add 1,881 megavolt amperes (MVA) of transformer capacity and 791 kilometers (km) of new transmission lines and upgrade 399 kilometers (km) of the existing 66 kilovolt (kV) and 132 kV transmission lines. To utilize loan savings, the number of subprojects was raised twice during implementation of the tranche 3 project: to 117 in August 2015 and 128 in September 2017, 93 of which were completed by the tranche and MFF closing date of 30 June 2018. The government financed the remaining 35 unfinished subprojects, 23 of which were completed in May 2019 and the rest are targeted for completion in September 2019.
At completion, the project achieved its intended outcome of rehabilitated, augmented, and expanded power distribution systems, exceeding 2 of its 3 outcome targets. Against the revised target of 2,396 MVA, 3,496 MVA of additional distribution capacity was installed by 2018. Transmission and distribution losses were reduced from 20.5% in 2012 to 17.95% in 2017, against a target of 19.50%. The energy savings target was also substantially achieved, with the project saving 236.38 gigawatt-hours (GWh) of energy in 2017, as compared to its 274 GWh target.
Attainment of its intended outcome enabled the project to significantly contribute to removing distribution system constraints by 2018. Electricity sales consequently rose by 6,000 GWh during the same year. Village electrification rate increased from 76% in 2011 to 82% in 2017. Outages for 132 kV feeders, comprising 94% of the project scope, were reduced by 81% between 2012 and 2017, although overall outages in the Pakistan Electric Power Company (PEPCO) system declined by just 3%. Overall thus, the project was able to achieve its envisaged impact to provide reliable and quality power supply and expanded service coverage.
PEPCO was the project executing agency and the country’s eight DISCOs were the implementing agencies.