Lessons

Horizontal Tabs

Lessons
Background

In mid−2000s, Madhya Pradesh in central India suffered from high electricity losses and poor service levels due to antiquated electrical distribution systems, particularly in the rural areas. This was the result of many years of insufficient funding for the expansion and maintenance of the systems. Over time, the decades-old wiring and equipment caused numerous and prolonged power outages, low voltage, and an increasing inability to connect new consumers. Extensive power theft because of illegal connections and a lack of metering exacerbated the problem. As the state’s population grew and farmers relied increasingly on irrigation, the need for better power distribution became urgent.

In response, the government of Madhya Pradesh developed a road map that called for the expansion of the power transmission system and systemic refurbishment of the distribution system. Following the restructuring of the Madhya Pradesh State Electricity Board that created 5 independent generation, transmission, and distribution companies, the state government, through the Ministry of Finance, requested for a $620 million-loan from the Asian Development Bank (ADB) to cover part of the $1 billion investment requirement of the road map.

The Madhya Pradesh Power Sector Investment Program was developed as a multitranche financing facility (MFF) to facilitate individual loans to the transmission and distribution companies over 5 years. It was delivered in 6 tranches, developed as individual loans, with each loan supporting a specific project. Approved in August 2007 for a loan of $166 million, project 5 focused on expanding and improving the distribution systems in the rural areas. It also supported institutional and capacity development of the 3 distribution companies (DISCOM) earlier created.

Although some changes and reductions in works were made, the outputs identified at appraisal were generally achieved by DISCOM−C in the central part of the state, DISCOM−E in the eastern part, and DISCOM−W in the west. New high-voltage distribution systems were constructed; inefficient low-voltage lines were converted to high-voltage lines; aged transformer substations were renovated and modernized, and new ones were built; and information technologies were enhanced through the introduction of a supervisory control and data acquisition system and transformer metering.

Technical optimization was ensured to improve the project design based on actual conditions. Tapping at the nearest connection, which reduced the length of distribution lines to be converted, and the use of global positioning system (GPS) in surveys and testing were successfully shown as good examples of technical optimization in rural electrification. Overall, the project helped alleviate electricity shortage and improve system reliability. The resulting improved services fostered economic growth and better living conditions in the project areas.

Implementation took longer than estimated, due to the unforeseen long time it took for the distribution cable and equipment to be procured and the termination of 12 works contracts. Appraisal cost estimate was $270.20 million but actual project cost totaled $163.80 million. Utilized ADB loan was $134.1 million.

ADB’s South Asia Department rated the project successful. DISCOM−C, DISCOM−E, and DISCOM−C were the executing agencies. A dedicated project management unit in each DISCOM took charge of implementation.

Project Information
Project Name: 
Madhya Pradesh Power Sector Investment Program (Tranche 5)
Report Date: 
July, 2017
Main Sector: 
Country: 
Project/Modality: 
Loan
Report Rating: 
Successful

Browse Lessons By:

Evaluation-Lessons.org uses cookies to improve your user experience. To learn more, click here to view our cookie policy. By clicking on OK or continuing to use the site, you agree that we can place these cookies.