At the request of the Government of India (GOI), the Asian Development Bank (ADB) approved in March 2006 a 4-tranche, $300 million multitranche financing facility (MFF) to help implement the Uttarakhand Power Sector Investment Program (UPSIP). The UPSIP aimed to meet the priority infrastructure requirements identified in Uttarakhand’s roadmap for state energy sector development.
Tranche 3 of the MFF, covering the construction of a 400/220/132 kilovolt (kV) Srinagar substation and capacity strengthening, was approved in January 2009. It was processed parallel to tranche 2 which, together with tranche 4, financed the construction of transmission lines for the evacuation of hydropower from Uttarakhand river basins to the northern grid of India. As with the other MFF tranches, it sought to contribute to the economic development of Uttarakhand and India’s northern region through expanded power supply at competitive prices. As of UPSIP preparation, Uttarakhand was among the poorest states of India, only 8 years old, and had an annual per capita electricity consumption less than half the national average.
Under tranche 3, the Srinagar substation was constructed according to the technical design set at appraisal. Two existing transmission lines had been looped-in-looped-out to the substation, significantly improving the operational flexibility and voltage regulation of the state grid. Moreover, the project had provisioned circuit bays whose transmission lines continued to be constructed even after MFF tranche 4 closed in March 2016. Installation of transmission lines of HPPs still under construction had also been provisioned under the project.
Site visits by the project completion report (PCR) mission confirmed the successful establishment of a sound power substation through the project. The evacuation of energy in 2016, the first year of project completion reached 1,274 gigawatt-hours (GWh)—equivalent to 290 megawatts at 50% load factor. At appraisal, the project envisaged evacuating 21,900 GWh of hydropower per year. Utilization of the facility is expected to increase over the next few years, with project outcome expected to be achieved by 2023 upon the completion of pipelined HPPs.
For capacity/institutional strengthening, the project consistently lagged in this area due to the late staffing of the project management office (PMO) and low level of ownership by the EA, the Uttarakhand Energy Department (UED). Capacity development commenced only in June 2015, and while the PMO prepared a 3-year training program, it was not fully implemented because of the project’s closing in March 2016. The project should have undertaken the appropriate training sessions, particularly those related to ADB requirements and operational procedures, early enough to support more effective project implementation.
Despite a 55-month delay in completion, the PCR rated the project successful. Actual total project cost was $34.24 million, 32% lower than the estimate at appraisal. Responding to a GOI request, ADB cancelled $2.6 million from the total tranche3 loanof $30.6 million in March 2015. At project closing, the net disbursed amount was $25.4 million, 91.26% of the available ADB $28.0 million loan.
The UED was the EA and the Power Transmission Company of Uttarakhand Limited (PTCUL), the implementing agency (IA).