Lessons

Horizontal Tabs

Lessons
Background

Viet Nam’s rapid economic progress has been accompanied by continually growing electricity demand for industrial development and private consumption. During 2000−2009, this demand grew at an average of 14% per year and, in 2011, was projected to grow at the same rate until 2015 and by 11% in 2016−2020. To meet these projected demand increases, the government adopted the Power Sector Development Master Plan (PDMP) VII, which identified multiple power generation and transmission projects to be implemented during 2011−2020 and laid out a detailed sector roadmap and reform framework. 

Against this backdrop, the Asian Development Bank (ADB) approved a $730 million multitranche financing facility (MFF) for Viet Nam’s Power Transmission Investment Program in December 2011. The program, to be delivered in four tranches, was to finance a portion of PDMP VII’s transmission and distribution investment requirements, estimated to cost a total of $7.78 billion.  Drawing on the success and lessons from two earlier ADB-financed transmission projects, it was to enhance the country’s power transmission network through three outputs (i) expanded transmission infrastructure, (ii) improved operational effectiveness and efficiency of the National Power Transmission Network (NPT), and (iii) project implementation support.

This report covers tranche 2 project, approved by ADB in December 2012 for a loan of $110.19 million.  The project focused on expanding the major 500 kilovolt (kV) transmission backbone line connecting central and south Viet Nam and two 220 kV transmission lines in Ho Chi Minh City, which were to contribute to achieving more balanced regional power loads, removing bottlenecks, facilitating power transfers, and reducing system losses and voltage fluctuations.

The transmission lines and associated facilities were completed as envisaged. However, as with the tranche 1 project, project 2 was unable to use the allocations for NPT operational and management capacity-building because of government regulation to restrict the use of official development assistance loans for nonphysical investments. Nevertheless, the NPT leveraged 2 ADB technical assistance projects and its own resources for capacity development especially in the areas of business development, planning and management, financial management, and transmission pricing calculation, enabling organizational and staff capacity buildup and progressive improvement in NPT financial performance. Project implementation support focused on safeguards compliance, identified under tranche 1 as an area where NPT was weak.

Completion of the planned outputs, notwithstanding significant delays in meeting social safeguard requirements, allowed the project to contribute to balancing the power loads in northern and southern Viet Nam.  It also helped the growth in power supply to keep pace with the actual 10.8% annual increase in demand during 2011–2016, and power system losses to fall from 10.2% in 2010 to 7.7% in 2016.

NPT, a subsidiary of the state-owned Viet Nam Electricity, served as the project executing agency.  The power project management boards established under the NPT for the central and southern regions acted as implementing agencies.

Project Information
Project Name: 
Power Transmission Investment Program (Tranche 2)
Report Date: 
September, 2018
Main Sector: 
Country: 
Project Number: 
Report Type: 
Project/Modality: 
MFF
SDG: 
Goal 9: Industry, Innovation, and Infrastructure
Loan Number: 
2959
Source of Funding: 
OCR
Date Approved: 
5 December 2012
Report Rating: 
Successful

Browse Lessons By:

Evaluation-Lessons.org uses cookies to improve your user experience. To learn more, click here to view our cookie policy. By clicking on OK or continuing to use the site, you agree that we can place these cookies.