Lessons

Horizontal Tabs

Lessons
Background

At the request of the government of Pakistan, the Asian Development Bank (ADB) approved an $810 million multitranche financing facility (MFF) for the Power Distribution Enhancement Investment Program in September 2008.  The approved MFF amount, to be provided in four tranches, represented 15.6% of the country’s total power distribution sector investment plan for 2008–2017.  The investment plan focused on improving the secondary transmission grid (STG) and distribution system and reducing transmission and distribution losses to ensure adequate power supply to meet the 8% per annum economic growth targeted by the government under its Medium-Term Development Framework, 2005−2010. 

Tranche 2 of the MFF, approved for a loan of $242 million in December 2010, was to finance physical investments mainly related to improving the STG through new or upgraded substations, new transmission lines, and additions or augmentations to transformers in existing substations.  Ninety-four percent of the tranche was to support STG investments while the rest was to finance the installation of capacitor banks to reduce technical losses. 

The tranche 2 project sought to improve power distribution infrastructure and management, as impact. Its intended outcome was removal of power system bottlenecks through distribution system rehabilitation, augmentation, and expansion, covering all eight distribution companies (DISCOs) of Pakistan.  Its expected output was completion of subprojects adding 3,380 megavolt-amperes (MVA) of transformer capacity and 387 kilometers (km) of new secondary 132 kilovolt (kV) transmission lines.

At appraisal, the project comprised 131 subprojects, 122 of which were on STG. During implementation, the number of subprojects rose to 167 because the DISCOs proposed additional subprojects against procurement savings. The 32 additional subprojects, all on STG, added 1,166 MVA of transformer capacity at 132 kV and 404 MVA at 11 kV.  By loan and MFF closing in June 2018, 164 of the subprojects had been completed, and those delayed by right-of-way and design-related issues were continued by the DISCOs using their own resources.   Including the output from the 3 ongoing subprojects, which all involve transmission line construction, Pakistan will have an additional 580 km of transmission line because of the project. A total of 394.8 km of these lines had already been installed by 2018.

Because of overachievement in its output targets, the project attained its intended outcome and impact, mostly in excess of targets. The 5,340 MVA of 132 kV power transformers that were installed enhanced the energy transformation capacity of the DISCOs all over Pakistan, except Karachi. The additional transmission lines facilitated power evacuation and connectivity with newly constructed and existing grid stations.  As a result, electricity sales went up by 24,341 gigawatt-hours (GWh) against the target of 12,000 GWh and village electrification reached 82% against the target of 78% in 2017. 

However, lack of generation capacity during peak electricity demand and system constraints in the transmission network of the National Transmission and Despatch Company, which operates all the 220 KV and 500KV grid stations and transmission lines in the country, impeded the project from achieving its target of reducing electricity outages in the Pakistan Electric Power Company (PEPCO) system by 20%.  The recorded outages at all voltage levels (132/66/11 kV) in the PEPCO system rose by just 1% between 2009 and 2017.  Nevertheless, the outages for 132 kV feeders, which comprised 94% of the project scope, were cut by 19% during the same period.

The project had the PEPCO as executing agency and the DISCOs as implementing agencies.

Project Information
Project Name: 
Power Distribution Enhancement Investment Program - Tranche 2
Report Date: 
August, 2019
Main Sector: 
Country: 
Project Number: 
Report Type: 
Project/Modality: 
MFF
SDG: 
Goal 9: Industry, Innovation, and Infrastructure
Goal 8: Decent Work and Economic Growth
Loan Number: 
2727
Source of Funding: 
OCR
Date Approved: 
14 December 2010
Report Rating: 
Successful

Browse Lessons By:

Evaluation-Lessons.org uses cookies to improve your user experience. To learn more, click here to view our cookie policy. By clicking on OK or continuing to use the site, you agree that we can place these cookies.