As it marked the return of international financers to hydropower following the World Commission on Dams report in 2000, the Nam Theun 2 Hydroelectric Project received unprecedented global scrutiny. In response, environmental and social impacts and revenue potentials were equally considered during project preparation, which comprised a lengthy, iterative, and consultative process, beginning with the first feasibility study in 1991 and continuing in the mid-1990s when international financers became involved. The project was an integral part of the medium- and long-term framework for economic growth and poverty reduction of the government of Lao People’s Democratic Republic (Lao PDR). By developing hydroelectric resources, it aimed to export electricity, earn foreign exchange to support the government’s poverty reduction and conservation initiatives, and promote regional and national economic development.
At government’s request, the Asian Development Bank (ADB) approved in April 2005 a $20 million sovereign loan to finance part of the government’s $87 million equity contribution to the project, estimated to have a base cost of $1,250 million at appraisal. In addition, it also provided the hydroelectric plant developer, the Nam Theun 2 Power Company Limited (NTPC), a direct loan without government guarantee of up to $50 million and a political risk guarantee of up to $50 million. The World Bank; the French Development Agency; the European Investment Bank (EIB); export credit agencies from France, Norway, Sweden, and Thailand; and a group of commercial banks also financed the project.
At completion, the project achieved five of its six planned outputs. A 1,070-megawatt (MW) transbasin hydroelectric plant, which diverts water from the Nam Theun River to the Xe Bang Fai River, was constructed. Four turbines generate about 995 MW for export to Thailand, and two turbines produce 75 MW for domestic use. Transmission infrastructure included a single circuit 115 kilovolt (kV), 70-kilometer (km) line to the domestic grid and a double circuit 500 kV, 138-km line to a new substation in Roi Et, Thailand. Access roads, bridges, and residences were also built to enable the construction and operation and maintenance of the plant, which began commercial operations in April 2010 under a 25-year Concession Agreement between the NTPC and the government.
Drawing on a comprehensive range of studies, including 19 project alternatives, environmental risk mitigation measures were developed and incorporated into the Concession Agreement and ADB financing agreements. The measures were implemented largely as planned, although there were challenges with the NTPC head construction contractor and subcontractor performance on occupational health and safety management, site erosion, biomass clearance in the reservoir area, and solid waste management. Non-compliances only dissipated with the completion of construction. For the operational stage, the NTPC adopted an environment management system, which was certified to the International Organization for Standardization (ISO-14001) and is annually reviewed.
A social development plan (SDP) for resettling all households affected by land acquisition and managing all social impacts, including indirect ones downstream of the project and impacts on ethnic minorities, was likewise formulated and subsequently implemented. A total of 1,310 households were relocated; by 2011, their incomes improved beyond the national rural poverty line. The re-settlers also benefited from the new dwellings, infrastructure, education, and health services provided under the project, and until the lapse of the Concession Agreement, will receive support from the NTPC-financed $750,000 a year Nam Theun 2 Development Fund.
To offset the biodiversity loss it was causing, the project intended to protect the Nakai Nam Theun national protected area (NNT-NPA) and its corridors from illegal logging. Ineffective implementation of the protection measures that were identified was however evident in the continued wildlife poaching and illegal timber extraction throughout project duration. Timber extraction, which was brought under control only by the Prime Minister’s national decree in 2016, continues to be addressed by the ongoing NTPC environmental management system.
Successful delivery of most of the planned outputs enabled the project to achieve its intended outcomes. From 2011 to 2018, the project exceeded its target to export 5,354 GWh of electricity to Thailand and provide 200 GWh of electricity to domestic consumers. The innovations by the project ─ including social development and environmental protection as key objectives, high quality and detailed environmental and social planning that addressed an extensive range of issues, and the allocation of project revenues to help eradicate poverty and conserve the environment ─ set benchmarks for the hydropower sector, locally and globally. Completion of the project spurred the implementation of several hydropower development initiatives led by independent power producers in the country. As of end-2017, government poverty reduction allocations reached $195.2 million, surpassing its $180.4 million net revenues from the hydroelectric plant since operation.
The Ministry of Industry and Handicrafts was the initial project executing agency. Following the power sector restructuring in 2006, the Ministry of Energy and Mines assumed coordination and project administration responsibilities. The NTCP, responsible for civil works, was also jointly responsible with the government for implementing the project’s environmental and social safeguard.