Lessons

Horizontal Tabs

Lessons
Background

In October 2007, the Asian Development Bank (ADB) approved a $273 million multitranche financing facility (MFF) for the Rajasthan Urban Sector Development Investment Program.  The MFF or investment program was designed to improve the urban environment; promote ongoing reforms for sustainable, efficient, and responsive urban service delivery; and close the development gap in the state through increased economic growth, reduced poverty, and sustained improvements in the urban environment and quality of life of 1.6 million people in 15 urban local bodies (ULBs).  It had two components: (i) improvements in urban infrastructure, including water supply, wastewater management, solid waste management (SWM), urban drainage, road rehabilitation and safety, and social and cultural heritage infrastructure; and (ii) capacity development and implementation support.

The MFF was provided in three tranches.  Tranche 1, which comprised a $60 million loan approved along with the MFF, supported project 1 that closed in December 2014.  Tranche 2, approved for a $150 million sector loan in January 2009, supported project 2, the subject of this report that, along with project 3 and the MFF, closed in June 2017.   

At appraisal, project 2 was expected to benefit 12 ULBs by (i) improving the access to treated, piped water supply of 1.2 million people or 90% of the population in 10 ULBs; (ii) providing sewerage facilities, including sewage treatment plants (STPs) in high density areas in seven ULBs, and reducing the volume of wastewater discharged to water bodies; (iii) rehabilitating drainage outfalls and constructing new roadside drains in three ULBs with a high risk of flooding; (iv) improving the traffic flow and travel times in five ULBs; and (v) improving institutional capacity, including technical and financial resources.

At completion, the project achieved 11 of its 12 output targets, enabling it to contribute the following to ADB’s results framework: (i) 259,208 households in 10 ULBs provided with new or improved water supply, (ii) 54 million liters per day (mld) added to wastewater treatment capacity in seven ULBs, (iii) 1,185 kilometers of water supply pipes installed or upgraded,  and (iv) 400 hectares of land improved through drainage and/or flood management.  All sample subprojects appraised during processing were implemented, allowing the project to achieve all its outcome targets. 

The water supply component resulted in asset creation; production, pumping and distribution improvements; and reduction in unaccounted-for-water and operation and maintenance (O&M) cost thereby providing all households in the project 2 areas with regular and reliable service, and additional quantity of water. The wastewater management component enabled asset creation and systemic improvements and developed safe disposal systems for sewage and protected water bodies. Sewerage facilities developed in eight hitherto unserved ULBs exceeded the target of seven ULBs.  The discharge of untreated wastewater to water bodies consequently dropped by more than 20 mld.

Besides the construction of new roadside drains, the urban drainage component rehabilitated drainage outfalls in two ULBs, reducing the incidence of flooding and the number of days the ULBs are impacted and benefitting more than 0.68 million people. The urban transport component improved the mobility of more than 1.76 million residents in nine ULBs, exceeding the target of five ULBs.  It consequently enhanced the poor’s access to economic opportunities, reduced travel times from an average of 40 minutes per crossing to less than 5 minutes during peak hours, cut travel costs, and diminished accidents at the intervention sites.

Recognizing the risk that ULBs might not be able to generate enough revenues to manage and maintain the existing and newly acquired assets, the loan covenanted that the state government shall ensure adequate O&M of the project facilities through budgetary allocations or other means, to be provided to the investment program management unit (IPMU), the appropriate ULB, or line agencies, during and after subproject completion. As of loan closing, ULBs and state-level bodies had consistently been able to meet the O&M costs of all urban services through well-structured and planned budgetary allocations.

On-the-job learning opportunities were provided to the implementing agency staff, consultants, and contractors.  Financial management systems were improved.  Training programs conducted effectively reoriented the staff of ULBs and state-level bodies toward the professionalization of municipal services and better urban governance.

As with the investment program, project 2 had the Local Self Government Department of Rajasthan as executing agency.  The IPMU served as the overall implementing agency, supervising the work of the investment program implementation units in each project town.

Project Information
Project Name: 
Rajasthan Urban Sector Development Investment Program (Tranche 2)
Report Date: 
June, 2019
Country: 
Project Number: 
Report Type: 
Project/Modality: 
Sector Loan
SDG: 
Goal 11: Sustainable Cities and Communities
Goal 9: Industry, Innovation, and Infrastructure
Goal 6: Clean Water and Sanitation
Goal 8: Decent Work and Economic Growth
Goal 1: No Poverty
Loan Number: 
2506
Source of Funding: 
OCR
Date Approved: 
19 January 2009
Report Rating: 
Successful

Browse Lessons By:

Evaluation-Lessons.org uses cookies to improve your user experience. To learn more, click here to view our cookie policy. By clicking on OK or continuing to use the site, you agree that we can place these cookies.