Lessons

Horizontal Tabs

Lessons
Background

Known for its large tea and petroleum industries, Assam has the largest economy in the northeastern region of India.  However, the state has lagged behind the rest of India in terms of growth and investment climate, and its economic activities have been significantly constrained by inadequate power supply and limited access to electricity.  One of the bottlenecks in Assam’s power sector was the limited capacity of its transmission and distribution (T&D) systems, which made it difficult to deliver reliable power to consumers.

To help address the situation, the Asian Development Bank (ADB) approved a multitranche financing facility (MFF), amounting to $200 million, for the Assam Power Sector Enhancement Investment Program in November 2009.  The MFF was designed to specifically support the government’s T&D sector investment program, which aimed to (i) strengthen power transmission capacity to deliver reliable and affordable electricity, (ii) improve access to electricity, (iii) enhance efficiency and quality of power supply, (iv) fully operationalize unbundled utilities of the Assam State Electricity Board (ASEB), and (v) promote private sector participation through innovative distribution franchising models. It planned to provide a solid foundation for a sustainable state power sector with increased transmission and distribution capacity to support inclusive economic growth and was originally designed to have three tranches, but a fourth tranche was approved in November 2014.

Tranche 1 project, the focus of this report, was approved in November 2009 for a loan of $60.3 million.  It comprised 6 physical investment subprojects involving capacity addition in transmission lines and transformation capacities, as well as a monitoring system. It also included technical assistance for institutional capacity development in business process reengineering, human resources management, financial management and audit, private sector participation, and renewable energy development. Its expected impact was a sustainable state power transmission sector to support inclusive economic growth. Its intended outcome was enhanced transmission capacity and quality with physical and institutional capacity development, which was to be achieved through 3 physical outputs and 4 nonphysical outputs.

At completion, the project delivered all its intended physical outputs.  There was a slight reduction in the length of the 132-kilovolt transmission lines actually constructed because of optimization. To utilize loan savings, upgrading to optical pilot ground wire, originally planned under tranche 2, was completed under tranche 1 as an additional physical output.  But the project’s accomplishments in relation to its intended nonphysical outputs fared differently: it was able to fully provide the necessary implementation support but only partially delivered those related to institutional capacity development, public-private partnership in distribution franchising, and renewable energy development.

Nonetheless, by fully delivering its planned physical outputs, the project contributed significantly to increasing transmission system capacity in Assam from 766 megawatts in 2008 to 1,960 megawatts in 2018, eased the transmission loading level from 95% in 2008 to 75%–80% in 2018, and reduced transmission losses from 6% to 3.55% during the same period. Other investments, including tranche 2, implemented during the same period, also contributed to the attainment of the project outcome.  Partial attainment of the institutional capacity development targets had however taken its toll on the project.  Safeguards related issues, due mainly to weak safeguard management capacity, significantly delayed project implementation, although they did not hamper the achievement of physical outputs and outcome targets. 

The increased capacity and improved performance of the transmission system facilitated the installation of new connections mainly in the rural areas, where access to electricity jumped from 22% to 66% of the population.  About 2.6 million households gained access to electricity over 2009–2019, resulting in increased economic activity and better living standards.

At appraisal, the government of Assam and the Assam Electricity Board (ASEB) were designated as executing agencies (EAs).  But under the state power sector reform process, the government of Assam formally dissolved and reorganized the ASEB, and in March 2013, transferred ASEB’s functions to three entities: the Assam Power Distribution Corporation Limited, the Assam Electricity Grid Corporation Limited (AEGCL), and the Assam Power Generation Corporation Limited. Since then, the AEGCL had served as the EA. The project management unit under the erstwhile ASEB continued to function as the coordinating agency.

Project Information
Project Name: 
Assam Power Sector Enhancement Investment Program - Tranche 1
Report Date: 
September, 2020
Main Sector: 
Country: 
Project Number: 
Report Type: 
Project/Modality: 
MFF
SDG: 
Goal 8: Decent Work and Economic Growth
Goal 9: Industry, Innovation, and Infrastructure
Loan Number: 
2592
Source of Funding: 
OCR
Date Approved: 
27 November 2009
Report Rating: 
Successful

Browse Lessons By:

Evaluation-Lessons.org uses cookies to improve your user experience. To learn more, click here to view our cookie policy. By clicking on OK or continuing to use the site, you agree that we can place these cookies.